Bond Engineering And Inspection Services

Combined Cycle Unit Steam Drum Replacement Third Party Quality Inspections

BEIS were engaged to provide third party in-process fabrication quality assurance inspection of a replacement steam drum to be installed at an Australian combined cycle power station. At the South Korean workshop, BEIS were able to verify the working quality documents against the physical works including:

BEIS were able to provide recommendations and improvements to the non-destructive testing plan to give the Client reassurance that the quality of their steam drum met the design and construction code requirements and it was fit for purpose for the remaining life of the plant.

High pressure steam assembly and evaporator riser nozzle inspection

High pressure steam drum hemispherical head inspection prior to fitting